February 18,2011
Building Sealant Work Schedule,2011
Dear residents,
Management has received updated schedule information from our contractors,Tritan Building Restoration. The schedule has been delayed due to weather conditions,and the dates shown below may change due to weather conditions.
Work is scheduled to begin on the west side of the building on March 7,2011.
In preparation for this,scaffolding / overhead protection will be built in the west laneway beginning February 24.
Work is scheduled to begin on the south side of the building on March 14,2011.
In preparation for this,scaffolding / overhead protection will be built over the Richmond St. sidewalk beginning during the week of March 7.
Residents with balconies on the south side of the building should plan to have their balconies cleared according to the detailed schedule,which will be provided for residents shortly. Please remove all patio furniture to allow the contractors space to work. If necessary,residents may store patio furniture in the courtyard at their own risk.
Work on south facing suites will run from approximately March 14 through to June.
Work on north facing suites will run from approximately June through to August.
Work on the east side of the building will run from approximately May through July.
Work from each swing stage will begin at the penthouse level and move down.
A more detailed schedule will be communicated shortly.
Management apologizes in advance for any inconvenience that this may cause and appreciates your patience,understanding and cooperation in this matter.
Should you have any further questions or concerns please contact the management office by calling 416-593-0693.
Yours very truly,
BROOKFIELD RESIDENTIAL SERVICES LTD.
Agents for and on behalf of Toronto Standard Condominium Corporation No. 1435
Cathy Johnson
Property Manager